All floor 3 concrete poured, pillars to floor 4 and most of floor 4 forms completed -- December 15, 2018
South of floor 4 poured and most of wooden forms for north 4 completed -- December 19, 2018
All of 4 forms completed and pillars to floor 5 being poured at south end -- December 19, 2018
All of floor 4 poured, pillars and forms for floor 5 mostly completed -- January 5, 2019
Floor 5 concrete at south and mostly done at north -- pillars reaching to floor 6 at south -- January 9, 2019
All forms for 6th floor completed and pouring concrete at south end of it -- January 16. 2019
Floor 6 completely concrete, completing forms for most of floor 7 -- January 24, 2019
Forms for floor 7 complete -- reaching for floor 8 -- February 2, 2019
Pouring concrete at south end of floor 7 -- February 5, 2019
Finishing reinforcements and utilities for north end of floor 7, starting forms for floor 8 -- February 11, 2019